To start percenting, the first thing you do is choose the floor (Page) that reflects where the work (labor) was performed.



Choose the Floor


Click on the Image Tab


Click the Page drop-down


Select the floor based on the page name (this is why it is helpful if the Project Manager collates drawings before sending out the Project).


on the Image Tab, using the Page Navigator, select the plan that indicates the floor on which work was performed