To start percenting, the first thing you do is choose the floor (Page) that reflects where the work (labor) was performed.
Choose the Floor
- Click on the Takeoff Tab
- Click the Page drop-down
- Select the floor or location based on the page name (this is why it is helpful if the Project Manager collates drawings before sending out the Project).