Skip to main content

Digital Production Control: Cannot Send DPC Changes

  • January 27, 2016
  • 0 replies
  • 15 views

Issue

The foreman (or foremen) cannot send DPC Changes back to Project Manager.

Discussion/Resolution

For the Foreman to send DPC changes, the following items need to be setup correctly:

  • The project must be set up for DPC correctly, see the Related articles for details
  • The Project Manager must send a complete DPC job file (DPC Package, not an OSP package) to the Foreman
  • The person creating the "DPC Changes" file must be listed as a Foreman on the DPC Tab of the Bid's Cover Sheet

On-Screen Takeoff/Digital Production Control Cover Sheet showing DPC Options.

Other Considerations

  • The Foreman must be licensed with a "dpc-foreman" license
  • Sending/Receiving requires an active Internet connection on the PC

If the Foreman is using Project Express and is receiving an error message about not being on Support, please contact Technical Support for assistance. There may be an issue with the Foreman's DPC license.


Related Articles